23/05/2026Planning a kitchen renovation in Malaysia? The biggest source of stress isn’t the design or the cost—it’s the timeline. How long does a kitchen renovation actually take? What order should things be done? And where do delays typically happen? This guide provides a realistic kitchen renovation timeline for Malaysian homeowners in 2026, based on EverGreen’s experience with hundreds of projects across Klang Valley.
Complete Kitchen Renovation Timeline
| Phase | Duration | Key Activities |
|---|---|---|
| 1. Planning & Design | 1-2 weeks | Consultation, 3D design, material selection |
| 2. Quotation & Agreement | 1 week | Final pricing, contract signing, deposit |
| 3. Production | 3-5 weeks | Factory cutting, edge banding, quality check |
| 4. Site Preparation | 2-3 days | Remove old cabinets, wall patching, plumbing |
| 5. Installation | 3-7 days | Cabinet fitting, countertop, hardware |
| 6. Finishing & Handover | 1-2 days | Touch-ups, cleaning, walkthrough |
Total: 6-10 weeks from first consultation to completed kitchen.

Phase 1: Planning & Design (1-2 Weeks)
This is where most homeowners rush—but shouldn’t. A thorough planning phase prevents costly changes later.
- Initial consultation — Discuss needs, budget, and style preferences (1 day)
- On-site measurement — Professional measurement of your kitchen space (1 day)
- 3D design — EverGreen provides free 3D renders for your review (3-5 days)
- Design revision — Most clients need 1-2 rounds of adjustments (2-3 days)
- Material selection — Choose panel type, door finish, countertop, and hardware (1 day)
Phase 2: Quotation & Agreement (1 Week)
- Receive detailed itemised quotation
- Review and negotiate if needed
- Sign contract and pay 50% deposit
- Confirm production start date
Phase 3: Factory Production (3-5 Weeks)
This is the longest phase and the one most affected by external factors.
- Week 1: CNC cutting, edge banding of panels
- Week 2: Panel assembly, hardware preparation
- Week 3: Quality control inspection, countertop templating (see NKBA renovation guidelines)
- Week 4-5: Countertop fabrication (quartz/granite), final QC
⚠️ Common delay: Custom quartz countertops from premium brands (Caesarstone, Silestone) may add 1-2 weeks if not in local stock.

Phase 4: Site Preparation (2-3 Days)
- Remove existing cabinets and fixtures
- Patch and repair walls
- Relocate plumbing points if layout changed
- Relocate electrical points (outlets, switches)
- Install new tiles/backsplash if applicable
Phase 5: Installation (3-7 Days)
- Day 1-2: Wall and tall cabinet installation
- Day 3-4: Base cabinets, drawer systems, internal fittings
- Day 5-6: Countertop installation and sealing
- Day 7: Doors, handles, and final adjustments
Phase 6: Finishing & Handover (1-2 Days)
- Silicone sealing around sink and countertop
- Touch-up any minor scratches
- Clean entire kitchen
- Client walkthrough and sign-off
- Pay remaining 50% balance
Common Questions
Can I speed up the process?
Yes, by having your design and material decisions ready quickly, and choosing materials that are in stock locally. EverGreen’s factory-direct model eliminates distributor delays.
Can I live in my home during renovation?
Yes, for cabinet-only renovations. If you’re also replacing tiles and plumbing, expect 3-5 days of disruption. Plan simple meals that don’t require a kitchen during installation days.
Detailed Kitchen Renovation Timeline Breakdown
Here’s exactly what happens during each phase of a kitchen renovation in Malaysia:
Phase 1: Planning & Design (Week 1-2)
- Initial consultation and measurement (1 day)
- 3D design and material selection (3-5 days)
- Quotation review and approval (2-3 days)
- Contract signing and deposit payment (1 day)
⚠️ Common delay: Homeowners who can’t decide on colours and materials. Come to the consultation with inspiration photos to speed up this phase.
Phase 2: Demolition & Preparation (Week 3)
- Remove old cabinets, tiles, and plumbing fixtures (1-2 days)
- Hacking of walls if layout changes (1 day, requires permit for HDB/strata)
- Plumbing and electrical rough-in (2-3 days)
- Floor and wall preparation (1-2 days)
⚠️ Common delay: Hidden water damage or termite damage discovered during demolition. Budget a 10% contingency for unexpected repairs.
Phase 3: Cabinet Fabrication (Week 4-6)
- Cutting and edge-banding of panels (2-3 days)
- Acrylic/laminate application (2-3 days)
- Hardware preparation and quality check (1 day)
- Transport to site (1 day)
This is where most contractors differ in quality. EverGreen fabricates in our own factory with CNC precision, giving us tighter tolerances and faster turnaround than workshops that cut by hand.
Phase 4: Installation (Week 7-8)
- Install base cabinets and level (1-2 days)
- Install wall cabinets (1 day)
- Install countertop template and measure (1 day)
- Countertop fabrication (3-5 days off-site)
- Countertop installation (1 day)
- Install backsplash and trim (1 day)
- Install hardware, handles, and accessories (0.5 day)
- Final adjustments and cleaning (0.5 day)
Phase 5: Handover (Week 8-9)
- Quality walkthrough with homeowner (1-2 hours)
- Demonstration of all hardware and accessories
- Warranty registration and care guide
- Retain 5-10% retention for 30-day defect liability period
How to Avoid Kitchen Renovation Delays
The #1 reason kitchen renovations run late in Malaysia: material delivery delays. Here’s how to prevent them:
- Confirm material availability before signing — Some quartz colours are imported and take 4-6 weeks. Ask your contractor to check stock before committing.
- Order appliances early — Built-in hobs, ovens, and range hoods often have 2-4 week lead times. Order when you sign the contract, not when installation starts.
- Don’t change your mind mid-project — Every change order adds 1-2 weeks. Finalise your design before fabrication begins.
- Get management approval early (for condos) — Strata management approval for renovation can take 1-4 weeks. Apply as soon as you sign the contract.
- Plan for festive seasons — Chinese New Year, Hari Raya, and Deepavali periods have reduced worker availability. Avoid starting demolition during these periods.
How much does a full kitchen renovation cost in Malaysia?
A complete kitchen renovation (demolition + new cabinets + countertop + backsplash + plumbing + electrical) typically costs RM15,000-RM50,000 depending on kitchen size and material choices. EverGreen’s packages start from RM12,000 for a condo kitchen (8-10ft, E0 + Blum + quartz top). Get a detailed quote based on your specific kitchen dimensions.
Can I live in the house during kitchen renovation?
Yes, but expect inconvenience for 3-4 weeks. Set up a temporary kitchen in the dining area with a portable induction cooker, rice cooker, and electric kettle. The dustiest phases (demolition and tile removal) last only 2-3 days. Your contractor should hang plastic sheeting to contain dust in the kitchen area.
Kitchen Renovation Budget Breakdown
Understanding where your money goes helps you make smart trade-offs:
| Item | % of Budget | Typical Cost (RM) | Can Save On? |
|---|---|---|---|
| Cabinet boxes + doors | 35-40% | 6,000-18,000 | ⚠️ Don’t compromise on E0 board |
| Hardware (Blum) | 10-12% | 1,500-5,000 | ⚠️ Blum is worth the investment |
| Countertop (Quartz) | 15-20% | 2,500-8,000 | ✅ Mid-range brands (Hanstone) |
| Backsplash tiles | 5-8% | 800-3,000 | ✅ Simple subway tiles |
| Plumbing + electrical | 8-10% | 1,200-4,000 | ❌ Must use licensed trades |
| Demolition + disposal | 5-8% | 800-3,000 | ❌ Proper disposal required |
| Appliances | 10-15% | 1,500-6,000 | ✅ Bundle deals available |
| Contingency | 5-10% | 1,000-5,000 | ❌ Always budget for surprises |
Where to invest vs where to save: Never compromise on cabinet structure (E0 board) and hardware (Blum)—these determine your kitchen’s lifespan. You can save on backsplash tiles (simple white subway tiles are timeless and cheap), appliance brands (middle-tier brands like Rubine or Fujioh are reliable), and decorative elements (add later as budget allows).
Kitchen Renovation Mistakes That Cost Time and Money
- ❌ Not planning for enough power outlets — Malaysian kitchens need 8-12 outlets minimum (rice cooker, kettle, toaster, blender, air fryer, induction cooker, refrigerator, range hood, dishwasher, water purifier). Add 2 extra for future appliances.
- ❌ Choosing appliances after cabinets are built — Always select your hob, oven, and range hood BEFORE the cabinet design is finalised. Built-in appliances have specific cutout dimensions that must be exact.
- ❌ Forgetting the water purifier point — Under-sink water purifiers need a dedicated water supply point and power outlet. Plan these during the plumbing phase, not after installation.
- ❌ Not checking management rules — Some condos restrict renovation hours (9am-5pm only), require specific contractor registration, or prohibit hacking on certain walls. Confirm all rules before starting.
- ❌ Skipping the retention clause — Always retain 5-10% of payment for 30 days after handover. This gives you leverage for defect rectification.
What to Do Before Your Kitchen Renovation Starts
Preparation makes the difference between a smooth renovation and a stressful one. Complete this checklist before Day 1:
- Take “before” photos — Document the existing kitchen for insurance and comparison purposes.
- Clear out all cabinets — Pack kitchen items into labelled boxes. You’ll need them for the temporary kitchen setup.
- Set up a temporary kitchen — Move microwave, kettle, rice cooker, and essentials to the dining area. Stock up on disposable plates and utensils for the renovation period.
- Confirm access for contractors — Provide parking details, lift access (for condos), and working hours. Inform neighbours about the renovation schedule as a courtesy.
- Arrange pet care — Construction dust and noise are stressful for pets. Arrange for them to stay elsewhere during the demolition phase (Week 3).
- Review the contract carefully — Ensure all specifications (board grade, hardware brand, countertop material, delivery date) are documented in writing. Verbal agreements are not enforceable.
Start Your Kitchen Renovation
Book a FREE on-site measurement and get your personalised renovation timeline.